Moving from prototype to mass production is not a single step. It is a series of evidence-based gate reviews. This checklist maps the gates Jaycon runs for injection molded products: Phase 0 design freeze, EVT, DVT, PVT and mass production. Use it to align engineering, tooling, quality and supply chain before you cut steel, approve PPAP or ship first parts.

Quick definition
A pre-production readiness checklist turns launch risk into a structured gate review. Each gate should have a clear checkpoint, evidence requirement, owner and pass/fail/hold decision before the program moves forward.

How to Use This Checklist

Gate-based reviews: Treat each phase as a formal review gate. Do not advance until every item is pass, resolved with an approved deviation, or assigned as a tracked action.

Owner-assigned tasks: Each row needs an accountable owner. For cross-functional programs, use a RACI model so engineering, quality, supply chain and the molder know who signs each item.

Evidence required: Every checkpoint should point to evidence such as a CMM report, first article inspection, material certificate, mold trial photo log, SOP, control plan or PPAP document.

Pass, fail or hold: Use pass/fail/hold decisions instead of vague status updates. A hold can still move forward if the deviation is documented, risk-rated and approved by the right stakeholders.

Pro tip
Print the downloadable PDF and post it in your NPI war room. Cross off items in real time during gate reviews and keep the Excel version as the live action tracker.

Figure 1. Injection molding pre-production phase gates from design freeze to mass production.

Phase 0: Design Freeze and DFM Sign-Off

Gate objective: Engineering and the molder agree that the design is tooling-ready. This gate prevents a prototype CAD file from moving into tooling before drawings, materials, tolerances and mold strategy are locked.

#CheckpointEvidenceOwnerP/F/H
0.12D/3D drawings released: STEP and PDF with CTQs, GD&T and finish callouts per zoneDrawing rev in PLMME 
0.2DFM review completed and signed: draft, wall thickness, undercuts, gate/ejector locations and shrink compensationDFM report and redlinesMolder 
0.3Material spec locked: grade, color, dry spec, regrind limit and required certificationsMaterial spec sheetME/Purchasing 
0.4BOM finalized: all components, inserts, hardware, packaging and labelsBOM rev in ERPPM 
0.5Tolerance stack-up analyzed: critical dimensions verified as feasibleStack-up reportME 
0.6Regulatory requirements documented: UL, FDA, RoHS, REACH, flammability or biocompatibilityCompliance matrixQA/RA 
0.7Mold class selected per volume, life requirement and expected cavitationTooling quoteMolder 
0.8Project timeline baselined with T0, T1, T2, PPAP and MP dates plus buffersMilestone trackerPM 

Exit criteria: Design is tooling-ready, DFM is signed, material is locked, mold class is selected and no unresolved design risks remain without an approved deviation.

Phase 1: EVT – Engineering Validation Test (T0 to T1)

Gate objective: First molded parts prove the concept. Major mold debugging and adjustments are expected at this stage, so the goal is not perfection. The goal is to capture data, identify defects and build a clean T1 action plan.

#CheckpointEvidenceOwnerP/F/H
1.1T0 trial scheduled: mold on press, water, electrical and hot runner verifiedMold trial planMolder 
1.2Material dried and verified: certificate on file and dryer logs match specDryer log and COAMolder 
1.3T0 shots produced: short shots acceptable, but photos, weights and cycle time are capturedT0 photo log and shot dataMolder 
1.4Critical dimensions measured on 5 parts and compared to the printCMM or optical reportQA 
1.5Visual inspection completed for sink, flash, short shots, weld lines and blushDefect map and photosQA 
1.6Tooling adjustments listed: steel-safe vs. weld/EDM and schedule impact notedAdjustment trackerMolder 
1.7Gate, vent or ejector changes proposed with simulation or engineering rationaleEngineering change noteMolder/ME 
1.8T1 plan approved with scoped adjustments, timeline and production-intent materialT1 trial planPM 

EVT exit criteria: All pass/fail/hold items are resolved, T1 adjustments are scoped and no show-stopper defect remains open.

Phase 2: DVT – Design Validation Test (T1 to T2)

Gate objective: Parts are in spec, the process is becoming stable and the design is frozen before PVT. DVT is where dimensional performance, functional fit and cosmetic standards need to converge.

#CheckpointEvidenceOwnerP/F/H
2.1T1 trial completed using virgin production resin and production cycle parametersT1 process sheetMolder 
2.2Full FAI completed: 100 percent of drawing dimensions measured on 5 piecesFAI reportQA 
2.3Cosmetic inspection completed per acceptance standard with finish and ejector locations checkedCosmetic sign-off sheetQA/ME 
2.4Process capability Cpk >= 1.33 on CTQ dimensions using 30 consecutive shotsCpk reportQA 
2.5Material property verification completed for tensile, Izod, HDT or other required propertiesLab test reportQA 
2.6Assembly fit and function verified with mating parts, hardware and torque specsAssembly test reportME 
2.7Mold maintenance PM completed: clean, lube, wear inspection and water flow balancePM checklistMolder 
2.8Texture or finish applied if planned between T1 and T2Texture cert and photosMolder 
2.9T2 trial plan approved with only minor tuning expectedT2 planPM 

DVT exit criteria: FAI is 100 percent pass, Cpk is at least 1.33 on CTQs, no critical visual defects remain and the design is frozen.

Figure 2. Simplified checklist preview showing checkpoints, evidence, owner and pass/fail/hold status.

Phase 3: PVT – Production Validation Test (PPAP-Lite to MP)

Gate objective: The production line, packaging, quality system and supply chain are validated. This is where the team confirms that good parts can be produced repeatedly, inspected reliably and shipped without uncontrolled risk.

#CheckpointEvidenceOwnerP/F/H
3.1T2 trial completed with production-intent process and no tooling adjustments neededT2 process sheetMolder 
3.2PPAP Level 3 package submitted or customer-specific level preparedPPAP binderQA 
3.3Gage R&R completed on all inspection fixtures and CMM programsMSA reportQA 
3.4Process control plan live with reaction plans, SPC charts and sampling frequencyControl planQA 
3.5Packaging and labeling validated with ship tests, label durability and barcode scanPack validation reportSupply Chain 
3.6Work instructions and SOPs approved for setup, startup, in-process, shutdown and changeoverSOP docsMolder 
3.7Operators trained and certified on setup, quality checks and defect identificationTraining recordsMolder/HR 
3.8Supply chain secured for resin, mold spares, hot runner spares and color masterbatchPOs and agreementsPurchasing 
3.9Golden samples signed by customer, Jaycon QA and engineering, then stored controlledGolden sample logQA 
3.10Containment plan for non-conformance approvedContainment SOPQA 

PVT exit criteria: PPAP is approved, zero open SCARs remain, the control plan is active, golden samples are signed and supply chain status is green.

Phase 4: MP – Mass Production Green Light

Gate objective: The program has moved from launch validation into steady-state production. The focus shifts to consistency, OEE, SPC, preventive maintenance and continuous improvement.

#CheckpointEvidenceOwnerP/F/H
4.1First production lot released against the control plan with zero deviationsLot release recordQA 
4.2OEE tracking live with availability, performance and quality targets setOEE dashboardMolder 
4.3SPC charts active and all CTQs in control with Cpk >= 1.33 maintainedSPC softwareQA 
4.4Preventive maintenance schedule running for mold, press and auxiliary equipmentPM calendarMolder 
4.5Voice-of-customer loop established with 30/60/90-day check-insVOC logPM 

Common Failure Modes This Checklist Prevents

RiskWhat happensHow to prevent it
Advancing before DFM sign-offTooling changes, longer T1 corrections and unclear accountabilityHold gate until DFM report is signed or deviation is approved
Missing evidence linksGate reviews become opinion-based instead of data-basedRequire every row to reference a report, photo log, certificate or approval record
No owner assignedOpen items drift between engineering, QA, molder and supply chainAssign a named owner per checkpoint and review open items weekly
Skipping capability studiesParts may pass one inspection but fail in productionRequire Cpk on CTQs before PVT exit
Packaging validated too lateGood parts can still fail during shipping or customer handlingValidate packaging before MP gate approval

FAQs About Pre-Production Readiness for Injection Molding

What are T0, T1 and T2 in injection molding?
T0 is the first shot run from a new mold and is used to debug the tool. T1 is the first corrected trial using production-intent material and process parameters. T2 is final tuning before production validation.

What is the difference between EVT, DVT and PVT?
EVT validates design feasibility. DVT validates the design and process capability with FAI, Cpk and functional testing. PVT validates the production line, packaging, quality system and supply chain.

When should I run a production readiness review?
Run a gate review before each major phase transition, especially before T0, before T1 and before PPAP submission.

What documents are needed for PPAP Level 3?
Typical documents include design records, engineering change documents, DFM evidence, FAI, MSA or Gage R&R, control plan, PSW, appearance approval, material certifications and sample parts.

How long does pre-production take for injection molding?
A typical program takes 8 to 14 weeks after tooling starts, but complex multi-cavity tools or major design corrections can add 4 to 6 weeks.

Download the Pre-Production Readiness Checklist

Use the checklist as an Excel or PDF template for gate reviews. The template should include tabs for Phase 0, EVT, DVT, PVT, MP launch, RACI matrix and deviation log. For teams preparing to launch an injection molded product, Jaycon can also review the gate package before the next trial or PPAP submission.

Related reading

Get a quote with a pre-tooling DFM review. Upload a STEP file with your volume and resin and get tooling and piece pricing back before you commit to a gate. Start a quote.